EPE and ONS update grid-connection note for battery storage projects
The revised note for battery solutions bidding in the 2026 capacity-reserve auction details controls, protection, communications and grid-forming functions.
Follow global economy, business, finance, energy, climate and public affairs through original sources, sourced data and context.
The revised note for battery solutions bidding in the 2026 capacity-reserve auction details controls, protection, communications and grid-forming functions.
The energy ministry is seeking input across six themes, from grid connections and demand management to data, regulation and concentrated vehicle fleets.
Brazil’s electricity regulator ANEEL announced on 30 October that November’s tariff flag will be green, continuing the signal in force during October. This means no additional charge under the tariff-flag mechanism for the month.
The energy ministry proposed 2030 and 2035 reductions in emissions, fossil-fuel use and generation costs; final targets remain for the national energy council to decide.
The consultation examines effects on regulated remuneration for distributors and transmission concessionaires; comments are due by 30 October.
The energy ministry asked distributors to submit or amend purchase-need declarations for the A-1, A-2 and A-3 auctions by 30 October.
Brazil’s Energy Research Company (EPE) released its 2027 liquid-fuel price outlook for isolated electricity systems on 15 October. It projects an average diesel realization price of R$3.78 per litre, above R$3.42 in 2025 and the R$3.62 average expected for 2026.
EPE, CCEE and ONS said they placed the code for their jointly owned electricity operations and pricing model in an open repository on 8 October. EPE’s 15 October statement says outside users can inspect and test the software and propose improvements.
The ministry opened a 20-day consultation on two draft rules for developing models used in power planning, operations and short-term pricing.
The roadmap assesses climate risk through the interaction of hazards, exposure and vulnerability.
EPE says public lighting consumed about 13,300 GWh in 2024 and served roughly 94% of localities.
Source not verified: Click Petróleo e Gás reported on 10 October that three projects received connection capacity on 6 October; the ONS results notice was not located in this review.