Alabama gives Kiewit Massman Traylor notice to proceed on Mobile River Bridge

ALDOT issued a notice to proceed on 25 September 2026 to the Kiewit Massman Traylor design-build team for the Mobile River Bridge and Bayway project, which the governor’s office put at $3.2 billion in construction cost.

Reading sizeSources ↓Share story ↗
Conceptual illustration of transport, bridges and infrastructure connections.Illustration
Symbolic illustration

On 25 September 2026, the Alabama Department of Transportation (ALDOT), acting for the Alabama Toll Road, Bridge and Tunnel Authority, issued a notice to proceed to the Kiewit Massman Traylor (KMT) design-build team for the Mobile River Bridge and Bayway project on Interstate 10. Governor Kay Ivey announced on 29 September 2026 that she had formally authorized the start of construction. Her office described the project, with a construction cost of $3.2 billion, as the largest transportation infrastructure project in Alabama history.

The governor’s office said the notice followed the close of bond sales and federal financing earlier in September and was the final procedural step before construction. On 2 October 2026, ALDOT said state, federal and local leaders broke ground at Cooper Riverside Park in downtown Mobile, and that KMT had begun mobilizing after the notice to proceed. Governor Ivey was joined by U.S. Transportation Secretary Sean P. Duffy.

ALDOT described the $3.2 billion Phase One as a new six-lane, cable-stayed Mobile River Bridge, improvements to key interchanges and traffic flow, and restriping of the existing Bayway to provide six lanes of capacity across Mobile Bay. A new Bayway structure is planned for a future phase. ALDOT said construction is expected to take five years. Neither source states the design-build contract price.

Data

Key figures

Construction cost and scope

Construction cost, lane counts and expected construction time stated by the Alabama governor’s office and ALDOT.

Construction cost
3.2 billion USD
2026-09-29 · Observed
Lanes on the new cable-stayed Mobile River Bridge
6 lanes
2026-10-02 · Target
Lanes of capacity across Mobile Bay after Bayway restriping
6 lanes
2026-10-02 · Target
Expected construction duration
5 years
2026-10-02 · Target
Methodology

The $3.2 billion figure is the construction cost stated by the governor’s office, and ALDOT applies it to Phase One. The sources do not state KMT’s design-build contract price. Lane counts and the five-year construction period describe planned scope and expected duration, not completed work.

Updated:

Structured coverage

Subjects and places

Subject proposals

Geographic references

Only source-provided geographic references are shown. Opening an external map is optional. Optional story maps use OpenStreetMap. Opening a map sends your IP address and this site’s address to the map provider; location data remains readable as text without loading the map.

  • United States · Place role: Coverage · Place type: Country or area · Location precision: Regional
    Evidence
Taxonomy version: IPTC Media Topics 2026-Q2

Continue reading

Infrastructure

Graham Infrastructure wins C$33 million Agassiz-Rosedale Bridge rehabilitation

On 18 September 2026 British Columbia said it has awarded Graham Infrastructure LP a C$33 million contract to rehabilitate the Agassiz-Rosedale Bridge on Highway 9, with construction expected to take about three years.

Government of British Columbia (Ministry of Transportation and Transit)2 min read
Data included