RTE starts three grid construction sites in Normandy

The works include a 225 kV underground link, a 400 kV overhead line and a new substation.

Reading sizeSources ↓Share story ↗
Conceptual illustration of electricity generation, storage and connected data.Illustration
Symbolic illustration

RTE began three new construction sites in Normandy as part of the second phase of its Seine Loop Energy Transition project. In a 14 October release, the French grid operator listed work on the Roseaux substation at Saint-Jean-de-Folleville, a 225 kV underground connection between Noroit and Roseaux, and a 400 kV overhead line between Rougemontier and Roseaux.

RTE said the reinforcement is intended to connect low-carbon generation with new industrial and household users from 2029. The company says electricity use in the area could quadruple by 2035; that is a projection. Starting the three sites does not mean the project is complete or the connections are already in service.

Data

Timeline

Event in the official release

Summary of the energy-sector development reported by the source.

  1. · Occurred

    RTE starts three grid construction sites in Normandy

    The works include a 225 kV underground link, a 400 kV overhead line and a new substation.

Methodology

This is a descriptive record of the event reported by the source; it does not claim independent measurement or additional realized outcomes.

Updated:

Structured coverage

Subjects and places

Subject proposals

Geographic references

Only source-provided geographic references are shown. Opening an external map is optional. Optional story maps use OpenStreetMap. Opening a map sends your IP address and this site’s address to the map provider; location data remains readable as text without loading the map.

  • France · Place role: Coverage · Place type: Country or area · Location precision: Regional
    Evidence
Taxonomy version: IPTC Media Topics 2026-Q2

Continue reading

Energy

CRE approves 2,500 MW of new connection capacity for Fos-Lavéra

France’s regulator approved shared grid works intended to add 2,500 MW of connection capacity in Fos-Lavéra. With 600 MW existing, total capacity reaches 3,100 MW; gross cost is estimated at €636.4 million.

Commission de régulation de l’énergie1 min read
Data included