Net Power takes over Saulsbury EPC agreement for planned 123 MW Texas gas plant
Net Power took over EMPower’s owner position in a Saulsbury Industries EPC agreement priced at $196,711,035.70 for an approximately 123 MW gas facility; the assignment closed on 31 August 2026.
Event / data period: 2026-08-31
Published: · Updated:

Net Power Inc. said in an SEC filing dated 3 September 2026 that its indirect subsidiary Net Power, LLC acquired EMPower USA, LLC’s position as owner under an engineering, procurement and construction agreement with Saulsbury Industries, Inc. The assignment closed on 31 August 2026. The agreement, dated 15 December 2025, covers an approximately 123 MW reciprocating-engine natural gas power generation facility, with a total contract price of $196,711,035.70.
Saulsbury remains the turnkey contractor for engineering, procurement, construction, pre-commissioning, commissioning, start-up and testing. The scope includes ten Wärtsilä engine-generator sets, balance-of-plant systems and the project substation. Saulsbury consented to the project’s relocation from Ector County, Texas, and Net Power intends to deploy the position at its Project Permian site in West Texas. The consideration included a premium of $40.0 million and reimbursement of $18,947,272.70 that EMPower had paid under the agreement.
Work has been suspended since 1 July 2026 and is expected to resume after Net Power issues the full notice to proceed and pays a mobilization payment of $10,153,524.85. Saulsbury extended the deadline for both to 15 October 2026. The filing said no revised project schedule has been agreed, no final investment decision has been made and no power purchase or energy services agreement has been signed for the facility.
Data
EPC agreement and facility figures
Contract, transaction and facility figures stated in Net Power’s SEC filing of 3 September 2026.
- EPC agreement total contract price
- 196.711 million USD
- 2026-09-03 · Observed
- Premium in the consideration for the assignment
- 40 million USD
- 2026-09-03 · Observed
- Mobilization payment due on full notice to proceed
- 10.154 million USD
- 2026-09-03 · Observed
- Planned facility capacity
- ≈123 MW
- 2026-09-03 · Target
- Wärtsilä engine-generator sets in scope
- 10 engine-generator sets
- 2026-09-03 · Observed
Methodology
Contract price is the total under the EPC agreement, stated before any change-order increase and before price escalation amounts. The premium is part of the consideration for the assignment, and the mobilization payment falls due when the full notice to proceed is issued. Capacity is the approximate planned capacity of a facility that is not yet built.
Updated:
Subjects and places
Subject proposals
- Natural gasSuggested
- Subject suggested from the title or summary: gas plantwww.sec.gov ↗www.sec.gov ↗
Geographic references
Only source-provided geographic references are shown. Opening an external map is optional. Optional story maps use OpenStreetMap. Opening a map sends your IP address and this site’s address to the map provider; location data remains readable as text without loading the map.
- United States · Place role: Coverage · Place type: Country or area · Location precision: RegionalEvidence
- Explicit preserved editorial country/region; no city or national centroid inferredwww.sec.gov ↗www.sec.gov ↗