France’s energy regulator published a consultation on 22 October that places annual electricity equalisation funding for Mayotte grid operator EDM in a €12.3 million to €26.2 million range for 2027–2029. EDM’s €56.5 million annual cost request is not an approved expenditure or a final funding decision.

Reading sizeSources ↓Share story ↗
Conceptual illustration of electricity generation, storage and connected data.Illustration
Symbolic illustration

France’s energy regulator CRE has opened a consultation on preliminary funding for Electricité de Mayotte (EDM), the island’s electricity distribution operator, for 2027–2029. The document is dated 15 October and appeared on CRE’s consultation page on 22 October. It presents annual electricity equalisation fund (FPE) allocations between €12.3 million and €26.2 million. These are draft scenarios: CRE expects to make its decision between late 2026 and early 2027, and the consultation remains open until 18 November.

EDM requests €56.5 million in annual costs, 28% above the €44.1 million annual average recorded in 2022–2025 excluding Chido’s direct effects. That request is not an approved spend. CRE applies auditor and regulator adjustments to some costs, producing a low scenario of €43 million in annual costs and a €12.3 million average allocation. The high scenario retains EDM’s requested €56.5 million cost level and €26.2 million average allocation. The regulator leaves the choice within this range for after stakeholder comments and its assessment of whether costs reflect an efficient network operator.

How FPE and TURPE interact

The electricity equalisation fund shares regulated distribution costs among public network operators in France. TURPE, the network use tariff charged to electricity users, shapes each operator’s revenue from transporting electricity and connections. For EDM, CRE compares expected TURPE revenue with capital costs and net operating costs attributed to an efficient operator to calculate the annual FPE allocation. When costs exceed revenue, an allocation is due; if revenue exceeds costs, the operator can owe a contribution. FPE is therefore not the same as the gross cost budget EDM requested.

CRE’s preliminary calculation assumes EDM will receive an annual average of €30.3 million in TURPE revenue over 2027–2029. That is 46.7% above the €20.6 million average for 2022–2025. The regulator uses the tariff update as well as expected connections, subscribed capacity and energy delivered in its revenue assumptions. Higher revenue reduces the required FPE amount when other inputs are held constant, so the funding calculation cannot be read from rising costs alone.

Network growth and post-Chido investment

CRE expects activity on Mayotte’s network to grow during 2027–2029. EDM’s forecast shows network length up 33%, energy delivered up 22% and customer numbers up 11%. The consultation links the projections to demographic and economic growth and public infrastructure planned for 2025–2031, naming a new airport, desalination plant and hospital. In 2025 EDM operated about 1,300 kilometres of network, served 53,967 delivery points and transported 388 GWh. Those figures describe the reach and reference volume of Mayotte’s grid; they are not national France measures.

EDM seeks annual investment of €54.1 million, €29.9 million above its 2022–2025 average, a 124% increase. The request includes burying overhead medium-voltage lines, improving low-voltage safety in residential areas and installing a synchronous compensator after Cyclone Chido. It also highlights the Badamiers–Kawéni submarine lines and security work at the Longoni source substation. CRE says the evidence is not yet enough to assess the efficiency of some major projects’ choice of solution, schedule and sizing. It is therefore considering excluding associated amounts from the initial investment path. If EDM demonstrates the projects’ efficiency and costs, CRE may consider coverage through the ex-post CRCP adjustment account.

Operating costs and power-system losses

EDM requests €30.8 million a year in net operating expenditure outside the power system, 45.4% above the €21.2 million average recorded in 2022–2025 excluding Chido. The operator attributes the increase to staffing, catch-up maintenance and repairs, and higher IT maintenance costs. CRE has made a preliminary assessment and used an independent audit of this cost group. In the low scenario, it applies the auditor’s proposed adjustments and further CRE adjustments; the high scenario uses EDM’s request. The method shows that not every cost item automatically qualifies for equalisation.

Power-system expenses are assessed separately and largely consist of purchased network losses and system services. EDM asks for an average €5.2 million a year in 2027–2029, compared with €4.2 million in 2022–2025. The operator forecasts a 21% fall in the unit cost of purchasing lost energy but a 24% increase in total loss costs. It attributes the increase partly to non-technical losses after Chido and the expected time needed to return to pre-crisis conditions. CRE directly examined this cost component to set its lower scenario; the difference between the two estimates is not a settled payment.

A dispute over capital returns and risk

EDM seeks returns above the parameters used for TURPE 7 HTA-BT. Its requested parameters include a 2.8% asset margin, a 6.8% return on regulated equity and 2.8% borrowing cost. The operator cites interest-rate conditions and Mayotte’s geographic risk. EDM also seeks distinct treatment of asset bases, with different regulatory parameters for high-voltage assets.

CRE’s preliminary position does not include the geographic risk premium EDM requested. The regulator says existing tariff rules already account for costs and risks specific to non-interconnected areas. It proposes separate regulated asset bases: the Enedis TURPE 7 parameters for low and medium voltage, and the RTE TURPE 7 approach for high voltage. The preliminary parameters are a 2.5% asset margin, 2.9% return on equity and 2.1% debt cost for HTA-BT; for HTB, a 5.0% weighted average cost of capital including a 2.9% debt cost. These are consultation proposals, not a final tariff.

Incentives target connections and service quality

CRE’s proposal treats funding alongside incentives for performance and efficiency. During 2022–2025, EDM was broadly in line with targets on network losses and service quality. Its connection times for low-voltage customers at or below 36 kVA fell short of targets; CRE attributed this to a backlog of connection requests. The regulator welcomed EDM’s efforts to industrialise processing, reflected in improved handling times for applications made in 2024 and 2025, but proposes raising the level and caps of connection incentives in the next period. This is a distinct regulatory mechanism intended to reward measurable connection performance.

For continuity of supply, CRE says EDM’s criterion B improved by about 9% a year over the period, while social events affected average interruption duration. CRE had not incentivised the indicator in 2022–2025 because results had varied widely in 2018–2021. Given the improving trend, it is considering an incentive for criterion B in 2027–2029. EDM’s advanced metering project began in 2025 and is scheduled to continue through 2032; CRE proposes keeping the project-specific incentive levels already set for it.

Priority projects and the consultation timetable

CRE proposes incentives for timely delivery of two priority projects: commissioning the new SAWA network control tool by 1 January 2028 and completing the renewable energy connection scheme, S2REnR, by 31 December 2029. These deadlines are distinct from the investment review: SAWA concerns network operations and control, while S2REnR is a plan for connecting renewable generation. CRE also notes that the FPE review focuses on 2027–2029, unlike the preceding four-year period; the 2026 allocation had been decided separately because of Chido’s exceptional impact.

The consultation closes on 18 November 2026. Interested parties can respond through CRE’s online platform; contributors with confidential commercial information are asked to submit a version suitable for publication. CRE plans to issue the final decision on EDM’s FPE allocation between the end of 2026 and the beginning of 2027. The €12.3 million lower and €26.2 million upper annual figures therefore should not be read as funds already granted or payments settled. The final amount will depend on efficient-operator cost assessments, expected revenue, the evidence for investment proposals and consultation responses.

Data

Table

FPE cost and allocation comparison for EDM

EDM request and CRE preliminary lower scenario in its 2027–2029 consultation, compared with realized 2022–2025 averages.

Total costs to be covered44.156.5432022–2025 realized, excluding Chido direct costs; 2027–2029 request and CRE preliminary lower scenario.
Average FPE allocation23.526.212.32022–2025 realized, excluding Chido direct costs; 2027–2029 EDM request and CRE preliminary lower scenario.
Net operating costs outside power system21.230.8-Annual average; realized 2022–2025 excluding Chido, and 2027–2029 request. Lower scenario not separately quantified in summary table.
Power-system costs4.25.2-Annual average; 2022–2025 realized and 2027–2029 request.
Normative capital costs18.720.5-Annual average; 2022–2025 realized excluding Chido direct costs and 2027–2029 request.
TURPE revenue20.630.3-Annual average; 2022–2025 and 2027–2029 forecast, respectively.
Methodology

All numeric values are annual averages in million euros. 2022–2025 values are realized; 2027–2029 values are EDM requests or CRE preliminary scenarios, not approved allocations. Direct Chido costs are excluded from comparable baseline values. Null means the source does not provide a corresponding value, not zero. Geographic scope is the EDM-operated network in Mayotte only.

Updated:

Structured coverage

Subjects and places

Subject proposals

Geographic references

Only source-provided geographic references are shown. Opening an external map is optional. Optional story maps use OpenStreetMap. Opening a map sends your IP address and this site’s address to the map provider; location data remains readable as text without loading the map.

  • France · Place role: Coverage · Place type: Country or area · Location precision: Regional
    Evidence
Taxonomy version: IPTC Media Topics 2026-Q2

Continue reading

Energy

CRE approves RTE’s revised 2026 grid investment programme at €4.09 billion

France’s energy regulator approved a €4.09 billion revision to transmission operator RTE’s 2026 investment programme, 3.5% below the plan approved in February. CRE also reviewed actual 2025 spending and variances across project categories.

Commission de régulation de l’énergie (CRE)6 min read Data included
Energy

France changes how Tempo red days are selected, excludes 24 and 31 December

A 21 October CRE decision changes red-day selection for the Tempo electricity tariff and excludes 24 and 31 December. The new algorithm begins on 1 November 2026; earlier notice starts a year later.

Commission de régulation de l’énergie (CRE)7 min read Data included