Nexans named preferred supplier for Mallorca-Menorca power link
An agreement with Red Eléctrica starts a six-month engineering phase intended to lay the groundwork for a future EPCI contract.
Follow global economy, business, finance, energy, climate and public affairs through original sources, sourced data and context.
An agreement with Red Eléctrica starts a six-month engineering phase intended to lay the groundwork for a future EPCI contract.
OMIE’s auction file shows a lower daily average than Saturday but a higher peak, across 100 quarter-hour periods.
A tender published by ADIF in the BOE on 20 October covers rehabilitation of the high-voltage power supply line serving signalling and telecommunications installations on the Arenys–Maçanet section.
Andalusia’s territorial authority in Granada opened public information on an application to upgrade an existing medium-voltage overhead line in Guadix, in a BOE notice published on 19 October.
Spain published a decision accepting Enel Green Power España’s withdrawal of its preliminary administrative-authorisation application for the proposed El Clavel photovoltaic plant. The decision was signed on 20 May and appeared in the Official State Gazette on 31 October, closing file SGIISE/PFot-933.
Recurrent Energy announced on 15 October that the Villameca solar plant in Spain’s Castilla y León region had entered commercial operation. The Canadian Solar subsidiary reported 200 MWp of solar peak capacity, a power rating rather than a quantity of electricity already generated.
Arteche signed a syndicated financing agreement for a maximum €200 million on 30 October, the electrical-equipment group disclosed to Spain’s CNMV. The agreement is divided into two tranches.
The decision rejected the permit application for the Los Campillos project, which had a proposed installed power of 33.825 MW. It was published in the BOE on 2026-10-20.
The decision accepted the withdrawal of the application for the Nordés project, which had a proposed installed power of 67.2 MW. It was published in the BOE on 2026-10-20.
The decision accepted the withdrawal of the application for the Mistral project, which had a proposed installed power of 106.4 MW. It was published in the BOE on 2026-10-19.
The BOE published on 20 October an authorization for Red Eléctrica de España to expand the Brovales substation near Jerez de los Caballeros, Badajoz.
The decision rejected the permit application for the Ampliación El Páramo project, which had a proposed installed power of 50.88 MW. It was published in the BOE on 2026-10-17.