Spain authorizes 400 kV synchronous compensator at Brovales substation

The BOE published on 20 October an authorization for Red Eléctrica de España to expand the Brovales substation near Jerez de los Caballeros, Badajoz.

Reading sizeSources ↓Share story ↗
Conceptual illustration of electricity generation, storage and connected data.Illustration
Symbolic illustration

The authorization covers a synchronous compensator and its associated bay in the substation’s existing 400 kV section.

Synchronous compensators help manage reactive power and voltage on the grid. The decision authorizes construction; it does not report that the equipment has entered service.

Data

Table

Project figure in decision

Project value stated in the official decision.

Substation voltage400
Methodology

Value transcribed from the source; it must not be read as realized generation or completed construction.

Updated:

Structured coverage

Subjects and places

Subject proposals

Geographic references

Only source-provided geographic references are shown. Opening an external map is optional. Optional story maps use OpenStreetMap. Opening a map sends your IP address and this site’s address to the map provider; location data remains readable as text without loading the map.

  • Spain · Place role: Coverage · Place type: Country or area · Location precision: Regional
    Evidence
    • Explicit preserved editorial country/region; no city or national centroid inferredwww.boe.es ↗
Taxonomy version: IPTC Media Topics 2026-Q2

Continue reading

Energy

Spain rejected the permit application for Los Campillos

The decision rejected the permit application for the Los Campillos project, which had a proposed installed power of 33.825 MW. It was published in the BOE on 2026-10-20.

Boletín Oficial del Estado (BOE)1 min read Data included