FERC preliminarily finds Zushi Renewables’ 40-kW California hydro project qualifies
Staff said the four-turbine canal project meets criteria for conduit hydropower that does not require a licence.
Event / data period: 2026-10-15
Published: · Updated:

Zushi Renewables filed for the Arvin Edison Canal Hydrokinetic 1 project on 1 October and supplemented its notice on 13 October. Four 10-kW turbines would provide 40 kW of installed capacity along an irrigation canal operated by the Arvin-Edison Water Storage District near Bakersfield, California.
FERC staff preliminarily found that the project would not change the canal’s primary agricultural water-delivery purpose and meets the qualifying conduit hydropower criteria. That preliminary finding means the project would not require a licence or exemption from licensing. Comments and intervention motions are due by 16 November 2026.
Data
FERC schedule for Zushi’s conduit hydro project
Application and comment milestones stated by FERC in docket CD27-2-000.
- · Occurred
Application filed
Zushi Renewables filed for its conduit hydrokinetic project.
- · Scheduled
Comments and intervention deadline
Comments and intervention motions in docket CD27-2-000 are due by 5 p.m. Eastern Time.
Methodology
Filing dates and the comment deadline are transcribed from FERC’s notice.
Updated:
Subjects and places
Subject proposals
- Renewable energySuggested
- Subject suggested from the title or summary: Renewables, hydropowerwww.federalregister.gov ↗
Geographic references
Only source-provided geographic references are shown. Opening an external map is optional. Optional story maps use OpenStreetMap. Opening a map sends your IP address and this site’s address to the map provider; location data remains readable as text without loading the map.
- United States · Place role: Coverage · Place type: Country or area · Location precision: RegionalEvidence
- Explicit preserved editorial country/region; no city or national centroid inferredwww.federalregister.gov ↗