Samsung E&A signs EPC contract for SABIC Agri-Nutrients’ SAN-7 plant in Jubail

Samsung E&A signed an EPC contract with SABIC Agri-Nutrients on 9 September 2026 for the SAN-7 ammonia and urea complex in Jubail. The owner put the contract at approximately USD 3.465 billion.

Reading sizeSources ↓Share story ↗
Conceptual illustration of electricity generation, storage and connected data.Illustration
Symbolic illustration

Samsung E&A signed an engineering, procurement and construction (EPC) contract with SABIC Agri-Nutrients for the SAN-7 project at a ceremony on 9 September 2026 at SABIC’s headquarters in Jubail, Saudi Arabia. Samsung E&A said the contract is worth KRW 4.7 trillion, about USD 3.5 billion, and that it will carry out the EPC work exclusively. In a Saudi Exchange disclosure on 10 September 2026, SABIC Agri-Nutrients said its board approved the final investment decision and the EPC award on 9 September 2026, at a total cost of approximately USD 3.465 billion.

Samsung E&A said the plant is being built in the Jubail Industrial Complex in eastern Saudi Arabia and will use natural gas as feedstock. SABIC Agri-Nutrients described an ammonia plant of 1.2 million metric tons per annum, two urea plants of 2.6 million metric tons per annum combined, and a post-combustion carbon capture unit. It said the project is expected to raise its urea capacity from 4.8 million to 7.4 million metric tons per annum, an increase of approximately 54%.

SABIC Agri-Nutrients said construction is expected to start in the fourth quarter of 2026. It expects commissioning in the third quarter of 2030 for four months, followed by commercial production and project completion in the fourth quarter of 2030. The company said it will assess financing options, including loans and its own cash flows.

Data

Key figures

Contract and plant figures

Contract values and planned capacities stated by SABIC Agri-Nutrients in its Saudi Exchange disclosure of 10 September 2026 and by Samsung E&A on 11 September 2026.

Total cost of the EPC contract, owner’s disclosure (USD)
≈3.465 billion USD
2026-09-10 · Observed
EPC contract value, Samsung E&A (KRW)
4.7 trillion KRW
2026-09-11 · Observed
Ammonia plant capacity per year
1.2 million tonnes
2026-09-10 · Target
Combined capacity of the two urea plants per year
2.6 million tonnes
2026-09-10 · Target
SABIC Agri-Nutrients urea capacity per year after the project (4.8 million tonnes before)
7.4 million tonnes
2026-09-10 · Target
Methodology

The USD figure is the approximate total cost of the EPC contract in the owner’s disclosure. The KRW figure is the contract value in Samsung E&A’s release, which gives about USD 3.5 billion as its dollar equivalent. Both describe the same contract and must not be added together. Capacities are planned design capacities per year, not output achieved.

Updated:

Structured coverage

Subjects and places

Subject proposals

Geographic references

Only source-provided geographic references are shown. Opening an external map is optional. Optional story maps use OpenStreetMap. Opening a map sends your IP address and this site’s address to the map provider; location data remains readable as text without loading the map.

  • Saudi Arabia · Place role: Coverage · Place type: Country or area · Location precision: Regional
    Evidence
Taxonomy version: IPTC Media Topics 2026-Q2

Continue reading