Lindian keeps December first-concentrate target at Malawi rare-earth project
Lindian Resources issued a 16 October update on construction, mining and commissioning readiness at its Kangankunde rare-earths project in Malawi. The company said it remains on schedule to target first monazite concentrate production in December 2026.
Event / data period: 2026-10-16
Published: · Updated:

The company reported an ore stockpile of approximately 149,000 tonnes, around 24,000 tonnes or 19% higher than in September. The tonnage is derived from existing Ore Reserve estimates; concentrate production has not begun.
A 33 kV overhead line was commissioned to the transformer yard and two 1,250 kVA plant transformers returned to site. Site energisation is targeted for the first week of November, a company schedule rather than completed production.
Data
Ore stockpile
Reported approximate ore stockpile at Kangankunde in the October update.
| Approximately 149,000 tonnes in October 2026 | 149000 |
Methodology
Company-reported approximate stockpile quantity, derived from existing Ore Reserve estimates; not produced concentrate.
Updated:
Subjects and places
Subject proposals
- Business enterpriseSuggested
- Preserved editorial category/topic; broad candidate onlywww.prnewswire.com ↗
- Metal and mineral mining and refiningSuggested
- Subject suggested from the title or summary: mining, rare-earth projectwww.prnewswire.com ↗
- Construction and propertySuggested
- Subject suggested from the title or summary: constructionwww.prnewswire.com ↗
Geographic references
Only source-provided geographic references are shown. Opening an external map is optional. Optional story maps use OpenStreetMap. Opening a map sends your IP address and this site’s address to the map provider; location data remains readable as text without loading the map.
- Malawi · Place role: Coverage · Place type: Country or area · Location precision: RegionalEvidence
- Explicit preserved editorial country/region; no city or national centroid inferredwww.prnewswire.com ↗