Lindian Resources issued a 16 October update on construction, mining and commissioning readiness at its Kangankunde rare-earths project in Malawi. The company said it remains on schedule to target first monazite concentrate production in December 2026.

Reading sizeSources ↓Share story ↗
Conceptual illustration of industry, engineering and logistics connections.Illustration
Symbolic illustration

The company reported an ore stockpile of approximately 149,000 tonnes, around 24,000 tonnes or 19% higher than in September. The tonnage is derived from existing Ore Reserve estimates; concentrate production has not begun.

A 33 kV overhead line was commissioned to the transformer yard and two 1,250 kVA plant transformers returned to site. Site energisation is targeted for the first week of November, a company schedule rather than completed production.

Data

Table

Ore stockpile

Reported approximate ore stockpile at Kangankunde in the October update.

Approximately 149,000 tonnes in October 2026149000
Methodology

Company-reported approximate stockpile quantity, derived from existing Ore Reserve estimates; not produced concentrate.

Updated:

Structured coverage

Subjects and places

Subject proposals

Geographic references

Only source-provided geographic references are shown. Opening an external map is optional. Optional story maps use OpenStreetMap. Opening a map sends your IP address and this site’s address to the map provider; location data remains readable as text without loading the map.

  • Malawi · Place role: Coverage · Place type: Country or area · Location precision: Regional
    Evidence
Taxonomy version: IPTC Media Topics 2026-Q2

Continue reading

Business

Brazilian Rare Earths reports resource and drilling progress in Bahia

Brazilian Rare Earths’ report for the quarter ended 30 September summarized activity across its Rocha da Rocha province in Bahia, Brazil. The Monte Alto mineral resource was reported at 11.3% total rare-earth-oxide grade, while the company described new mineralization at Sulista South and an extension at Sulista East.

Brazilian Rare Earths1 min read Data included
Business

Aclara updates preliminary economics for Chile’s Penco rare-earth project

Aclara Resources reported an updated preliminary economic assessment for its Penco ion-adsorption clay project in Chile’s Biobío region. Announced on 19 October, the study presents a resource-based project scenario; the technical report has an effective date of 18 September 2026.

Aclara Resources1 min read Data included
Business

PLS approves A$1.9 billion P2000 lithium expansion

On 15 October, PLS made a final investment decision on its A$1.9 billion P2000 project at Pilgangoora in Western Australia. A new Jimmagunya processing plant is intended to raise spodumene-concentrate production capacity to about 2 million tonnes a year.

PLS Group1 min read Data included