Energy / WORLD

Italgas connects second biomethane plant to northern Italy reverse-flow hub

A Cortepila plant raises the Gazzo Veronese hub’s stated intake potential to six million cubic metres a year; two more connections are planned.

Reading sizeSources ↓Share story ↗
Conceptual illustration of electricity generation, storage and connected data.Illustration
Symbolic illustration

Italgas has connected a second biomethane producer to its Digital Reverse Flow hub in Gazzo Veronese, in northern Italy, bringing the hub’s potential annual intake to six million cubic metres, the company said on 22 October. The new connection links the Cortepila plant in San Giorgio Bigarello, in Mantua province, to the network. It is also the twentieth biomethane plant connected to Italgas’ distribution network, according to the company.

Cortepila produces renewable gas from agri-food residues, agricultural biomass and livestock effluent. It can inject up to about four million cubic metres a year into the network. To connect it, Italgas built a dedicated facility to receive and inject the gas and added a roughly 40-metre section of network. The new connection raises the Gazzo Veronese hub’s intake potential from two million to six million cubic metres annually, equivalent in the company’s estimate to the average consumption of about 6,500 households.

The Digital Reverse Flow hub was inaugurated in June and receives gas from connected biomethane plants. When production exceeds demand on the local distribution network, the system compresses and transfers the gas to regional and national transmission networks, making it available beyond the immediate area. The design addresses a constraint of distribution networks: local production may at times exceed local demand, while the wider system can absorb renewable gas elsewhere.

The first connected facility, operated by Società Agricola Villagrossa in Castel d’Ario, entered operation in July. Italgas says the next connections are expected from plants in Borgo Virgilio and Villimpenta, both in Mantua province, in the coming months. With four plants in operation, the hub could receive up to 12 million cubic metres of biomethane a year, which the company compares with the average consumption of about 13,000 households. This is a future capacity scenario dependent on those additional connections, not current intake.

Italgas says the system is fully digitalized and controlled by DANA, its Digital Advanced Network Automation platform. DANA is the company’s automation and remote-control system for managing network operations. Italgas presents the reverse-flow hub as part of a wider conversion of distribution networks into more flexible infrastructure able to handle growing amounts of renewable gas produced locally.

The new connection therefore expands both the number of producers able to inject biomethane and the amount the hub can potentially receive. The company’s release distinguishes actual current connections from the next two plants that are expected later. It does not report the hub’s measured daily flow, the annual amount actually injected, methane composition, lifecycle emissions or the amount of fossil gas displaced.

Biomethane is produced by upgrading biogas from organic material. At Cortepila, the company identifies agri-food residues, agricultural biomass and livestock effluent as feedstocks. The announcement does not provide their individual shares or say whether all feedstock is sourced locally. Italgas emphasizes that a digital reverse-flow installation can send surplus gas out of the local network and into the broader transport system.

Italgas says Gazzo Veronese has now reached half of its planned potential based on the first two connections. The next stated milestone is to connect the Borgo Virgilio and Villimpenta plants, after which the hub’s possible annual intake would double to 12 million cubic metres. The company gives no commissioning dates for those connections, so the timetable remains open.

Data

Key figures

Plants connected to the Gazzo Veronese hub

Existing connections and the next two plants identified by the company.

Currently connected plants
2 count
2026-10-22 · Observed
Additional plants expected
2 count
2026-10-22 · Forecast
Methodology

The first plant entered operation in July; the second connection was made on 22 October. Two additional connections are expected in coming months; plant count is not an observed gas volume or output.

Updated:

Structured coverage

Subjects and places

Subject proposals

Geographic references

Only source-provided geographic references are shown. Opening an external map is optional. Optional story maps use OpenStreetMap. Opening a map sends your IP address and this site’s address to the map provider; location data remains readable as text without loading the map.

  • Italy · Place role: Coverage · Place type: Country or area · Location precision: Regional
    Evidence
    • Explicit preserved editorial country/region; no city or national centroid inferredwww.italgas.it ↗
Taxonomy version: IPTC Media Topics 2026-Q2

Continue reading

Energy

Eni sets €1.3 billion extra dividend as nine-month production rises

The Italian energy group reported higher upstream output and a stronger 2026 cash-flow outlook after its third-quarter results. It also increased its buyback plan and outlined developments across oil, gas, refining and transition businesses.

Eni3 min read Data included
Energy

ENEA and IP set four-year cooperation on renewable energy carriers

Italy’s National Agency for New Technologies, Energy and Sustainable Economic Development (ENEA) and energy company IP announced a four-year memorandum of cooperation on 15 October. The work will focus on renewable energy carriers including hydrogen, e-fuels and biofuels.

ENEA1 min read Data included