DOE plans up to $150 million for Alaska transmission link

The Beluga-Healy project is expected to add a second high-voltage route across Alaska’s Railbelt, with total planned investment of $418 million.

Reading sizeSources ↓Share story ↗
Conceptual illustration of electricity generation, storage and connected data.Illustration
Symbolic illustration

The U.S. Department of Energy said on October 5 it intends to provide up to $150 million in Defense Production Act funding for Alaska’s Beluga-Healy transmission project. DOE described the planned project as a second high-voltage connection between Southcentral and Interior Alaska, combining the federal funding with $268 million in non-federal funding for an estimated total of $418 million.

The proposed line would run about 223 miles between Beluga and Healy. DOE says the additional route would improve reliability for communities and military installations, and could serve about 75% of Alaska’s population once complete. The announcement is an intent to deploy funding for development; it does not say the line is built or operating.

Data

Key figures

Beluga-Healy transmission project plan

DOE funding intent and project planning figures for a proposed Alaska transmission link.

Maximum planned federal funding
≤150 million USD
2026-10-05 · Target
Preliminary total project estimate
≈418 million USD
2026-10-05 · Estimate
Planned transmission line length
≈223 miles
2026-10-05 · Target
Methodology

The October 5 announcement gives a maximum planned federal contribution and a preliminary project cost estimate. The line is proposed, not operational.

Updated:

Structured coverage

Subjects and places

Subject proposals

Geographic references

Only source-provided geographic references are shown. Opening an external map is optional. Optional story maps use OpenStreetMap. Opening a map sends your IP address and this site’s address to the map provider; location data remains readable as text without loading the map.

  • United States · Place role: Coverage · Place type: Country or area · Location precision: Regional
    Evidence
    • Explicit preserved editorial country/region; no city or national centroid inferredwww.energy.gov ↗
Taxonomy version: IPTC Media Topics 2026-Q2

Continue reading