NEXTDC cuts FY27 guidance after Melbourne power delay
NEXTDC said on 21 October that the next grid-capacity increase for its M3 Melbourne data centre had been delayed to FY28 and revised FY27 guidance. The ranges exclude affected M3 customer contracts.
Event / data period: 2026-10
Published: · Updated:

Revised FY27 guidance excludes affected M3 customer contracts: A$475–500 million net revenue, A$245–265 million underlying EBITDA and A$4.5–5 billion capital expenditure. These are forward-looking company estimates.
Data
Reported figure
Value reported by the source; guidance and forecasts are not realized results.
| FY27 net revenue lower bound | 475 |
Methodology
Value and unit transcribed from the release.
Updated:
Subjects and places
Subject proposals
- EconomySuggested
- Preserved editorial category/topic; broad candidate onlywww.marketindex.com.au ↗
Geographic references
Only source-provided geographic references are shown. Opening an external map is optional. Optional story maps use OpenStreetMap. Opening a map sends your IP address and this site’s address to the map provider; location data remains readable as text without loading the map.
- Australia · Place role: Coverage · Place type: Country or area · Location precision: RegionalEvidence
- Explicit preserved editorial country/region; no city or national centroid inferredwww.marketindex.com.au ↗