# Dhofar II 125 MW wind project in Oman reaches financial close with 2027 operations target

> The 125-megawatt Dhofar II Wind Independent Power Project in Oman, developed by Sembcorp Utilities and OQ Alternative Energy through Naseem Dhofar SAOC, reached financial close. Comprising 20 turbines and expected to generate about 397 GWh annually under a 20-year power purchase agreement, the facility targets commercial operations in the third quarter of 2027.

- Canonical URL: https://newsverum.com/en/news/sembcorp-oq-dhofar-ii-125-mw-wind-project-oman-financial-close-2026
- Publisher: Newsverum
- Section: Energy
- Country: Oman
- Published: 2026-11-20T17:40:00+00:00
- Updated: 2026-11-20T17:40:00+00:00
- Event / data period: 2026-11-20
- Other editions: [Türkçe](https://newsverum.com/tr/news/sembcorp-oq-dhofar-ii-125-mw-wind-project-oman-financial-close-2026.md), [العربية](https://newsverum.com/ar/news/sembcorp-oq-dhofar-ii-125-mw-wind-project-oman-financial-close-2026.md), [Français](https://newsverum.com/fr/news/sembcorp-oq-dhofar-ii-125-mw-wind-project-oman-financial-close-2026.md), [Español](https://newsverum.com/es/news/sembcorp-oq-dhofar-ii-125-mw-wind-project-oman-financial-close-2026.md), [Deutsch](https://newsverum.com/de/news/sembcorp-oq-dhofar-ii-125-mw-wind-project-oman-financial-close-2026.md), [Português](https://newsverum.com/pt/news/sembcorp-oq-dhofar-ii-125-mw-wind-project-oman-financial-close-2026.md)

Global law firm Greenberg Traurig announced in Dubai on 20 November 2026 that the 125-megawatt Dhofar II Wind Independent Power Project in the Sultanate of Oman had reached financial close. According to the release, Greenberg Traurig advised Sembcorp Utilities as project sponsor and Naseem Dhofar SAOC as the project company throughout the development and project-financing process. While reaching financial close confirms that debt and equity agreements have been executed and conditions precedent for financing structure completion have been met, the announcement does not disclose the total capital cost of the project, the debt-to-equity ratio, or the identity of the lending banks.

The Dhofar II wind project is jointly developed by Sembcorp Utilities and OQ Alternative Energy through the special-purpose project company Naseem Dhofar SAOC. The facility is sited in the Wilayat of Shaleem and the Al Hallaniyat Islands within Oman's southern Dhofar Governorate. Pairing an international utility developer such as Sembcorp Utilities with OQ Alternative Energy—the clean-energy arm of Oman's state-backed energy group—follows the independent power producer framework used across the Gulf region to mobilize external project finance alongside domestic institutional participation.

On a technical level, the wind farm will consist of 20 wind turbines with a combined installed nameplate capacity of 125 megawatts, averaging 6.25 megawatts per turbine. Once commissioned, the installation is projected to generate approximately 397 gigawatt-hours of renewable electricity per year. Based on a 125-megawatt installed rating and an 8,760-hour calendar year, an annual output projection of 397 gigawatt-hours implies a net capacity factor of roughly 36.2 percent, reflecting the seasonal monsoon and coastal wind regime characteristic of the Dhofar Governorate. Nevertheless, the release does not name the wind turbine manufacturer, the engineering, procurement, and construction contractor, or the grid interconnection voltage.

All electricity generated by the Dhofar II wind farm will be sold to Nama Power and Water Procurement Company under a 20-year power purchase agreement. Nama Power and Water Procurement Company serves as the single buyer of wholesale electricity and desalinated water capacity in the Sultanate of Oman. Commercial operations are targeted for the third quarter of 2027. A 20-year contracted offtake schedule provides the long-term revenue visibility typically required by project-finance lenders, though the press release does not state the contracted tariff per megawatt-hour or specific curtailment and availability terms.

The legal advisory team acting for Sembcorp Utilities and Naseem Dhofar SAOC operated out of Greenberg Traurig's Dubai office. The engagement was led by Nicholas Kramer, head of Construction and Projects for the Middle East, and Angela Croker, head of the Project Finance Practice for the United Arab Emirates, supported by Of Counsels Lindsay Crawford and Anastasia Kastelskaya. Kramer and Croker noted that the transaction covered both development contracts and financing documentation through to financial close.

In its corporate background disclosure, Greenberg Traurig noted that it established its Middle East presence in 2023 with offices in Riyadh, Saudi Arabia, and Dubai, United Arab Emirates, before opening a third regional office in Abu Dhabi in 2025. Across its global network, the firm employs approximately 3,200 lawyers across 51 locations in the United States, Europe, the Middle East, Latin America, and Asia. That regional expansion reflects rising demand for cross-border project finance and infrastructure legal counsel as Gulf states tender utility-scale solar and wind concessions.

For Oman's electricity sector, adding 125 megawatts of wind capacity in the Wilayat of Shaleem and Al Hallaniyat Islands expands utility-scale non-hydrocarbon generation outside the northern industrial load centers. However, achieving the targeted commercial operation date in the third quarter of 2027 requires completing turbine transport, foundation civil works, erection of the 20 units, substation tie-in, and grid compliance testing within less than a year of the November 2026 financial close announcement.

The verified milestone on 20 November 2026 is the financial close of the 20-turbine, 125-megawatt Dhofar II Wind Independent Power Project developed by Sembcorp Utilities and OQ Alternative Energy via Naseem Dhofar SAOC under a 20-year power purchase agreement with Nama Power and Water Procurement Company. Follow-up verification should track turbine installation progress in Dhofar Governorate, grid synchronization, and whether commercial operations begin on schedule in the third quarter of 2027.

## Data

### Key reported figures

Selected figures transcribed from the cited primary source.

Methodology: Figures retain the source's stated period, scope and definitions. Announced targets, estimates and approximate figures are labeled by basis and qualifier. No missing value is inferred.

| label | value | unit | period | basis |
|---|---|---|---|---|
| Installed capacity of Dhofar II Wind Independent Power Project | 125 | MW | 2026-11-20 | target |
| Number of planned wind turbines at Dhofar II | 20 | count | 2026-11-20 | target |
| Duration of power purchase agreement with Nama Power and Water Procurement Company | 20 | years | 2026-11-20 | observed |

Sources: <https://www.prnewswire.com/news-releases/greenberg-traurig-represents-sembcorp-naseem-dhofar-on-development-and-financing-of-dhofar-ii-wind-ipp-in-oman-302946226.html> · Download data: [JSON](https://newsverum.com/api/v1/articles/sembcorp-oq-dhofar-ii-125-mw-wind-project-oman-financial-close-2026/data/reported-figures?lang=en&format=json) · [CSV](https://newsverum.com/api/v1/articles/sembcorp-oq-dhofar-ii-125-mw-wind-project-oman-financial-close-2026/data/reported-figures?lang=en&format=csv)

## Sources

- [Greenberg Traurig, Greenberg Traurig Represents Sembcorp, Naseem Dhofar on Development and Financing of Dhofar II Wind IPP in Oman](<https://www.prnewswire.com/news-releases/greenberg-traurig-represents-sembcorp-naseem-dhofar-on-development-and-financing-of-dhofar-ii-wind-ipp-in-oman-302946226.html>) (Source checked: 2026-11-20; Published: 2026-11-20)

---