# Lindian keeps December first-concentrate target at Malawi rare-earth project

> Lindian Resources issued a 16 October update on construction, mining and commissioning readiness at its Kangankunde rare-earths project in Malawi. The company said it remains on schedule to target first monazite concentrate production in December 2026.

- Canonical URL: https://newsverum.com/en/news/lindian-kangankunde-rare-earth-project-october-construction-update-2026
- Publisher: Newsverum
- Section: Business
- Country: Malawi
- Published: 2026-10-21T00:44:02+00:00
- Updated: 2026-10-21T00:44:02+00:00
- Event / data period: 2026-10-16
- Other editions: [Türkçe](https://newsverum.com/tr/news/lindian-kangankunde-rare-earth-project-october-construction-update-2026.md), [العربية](https://newsverum.com/ar/news/lindian-kangankunde-rare-earth-project-october-construction-update-2026.md), [Français](https://newsverum.com/fr/news/lindian-kangankunde-rare-earth-project-october-construction-update-2026.md), [Español](https://newsverum.com/es/news/lindian-kangankunde-rare-earth-project-october-construction-update-2026.md), [Deutsch](https://newsverum.com/de/news/lindian-kangankunde-rare-earth-project-october-construction-update-2026.md), [Português](https://newsverum.com/pt/news/lindian-kangankunde-rare-earth-project-october-construction-update-2026.md)

The company reported an ore stockpile of approximately 149,000 tonnes, around 24,000 tonnes or 19% higher than in September. The tonnage is derived from existing Ore Reserve estimates; concentrate production has not begun.

A 33 kV overhead line was commissioned to the transformer yard and two 1,250 kVA plant transformers returned to site. Site energisation is targeted for the first week of November, a company schedule rather than completed production.

## Data

### Ore stockpile

Reported approximate ore stockpile at Kangankunde in the October update.

Methodology: Company-reported approximate stockpile quantity, derived from existing Ore Reserve estimates; not produced concentrate.

| Measure | Tonnes |
|---|---|
| Approximately 149,000 tonnes in October 2026 | 149000 |

Sources: <https://www.prnewswire.com/apac/news-releases/lindian-resources-kangankunde-rare-earths-project-advances-towards-december-first-production-302910740.html> · Download data: [JSON](https://newsverum.com/api/v1/articles/lindian-kangankunde-rare-earth-project-october-construction-update-2026/data/kangankunde-stockpile?lang=en&format=json) · [CSV](https://newsverum.com/api/v1/articles/lindian-kangankunde-rare-earth-project-october-construction-update-2026/data/kangankunde-stockpile?lang=en&format=csv)

## Sources

- [Lindian Resources Limited](<https://www.prnewswire.com/apac/news-releases/lindian-resources-kangankunde-rare-earths-project-advances-towards-december-first-production-302910740.html>) (Source checked: 2026-10-21; Published: 2026-10-16)

---

Cite the canonical URL above. [Editorial standards and corrections](https://newsverum.com/en/editorial)