# i-80 Gold updates development schedule for Nevada projects

> The company outlined sequencing for Archimedes, Lone Tree and Mineral Point; its 2028 production range is a target.

- Canonical URL: https://newsverum.com/en/news/i80-gold-nevada-development-plan-update-october-2026
- Publisher: Newsverum
- Section: Business
- Country: United States
- Published: 2026-10-15T20:19:53+00:00
- Updated: 2026-10-15T20:19:53+00:00
- Source review period: 2026-10-14
- Other editions: [Türkçe](https://newsverum.com/tr/news/i80-gold-nevada-development-plan-update-october-2026.md), [العربية](https://newsverum.com/ar/news/i80-gold-nevada-development-plan-update-october-2026.md), [Français](https://newsverum.com/fr/news/i80-gold-nevada-development-plan-update-october-2026.md), [Español](https://newsverum.com/es/news/i80-gold-nevada-development-plan-update-october-2026.md), [Deutsch](https://newsverum.com/de/news/i80-gold-nevada-development-plan-update-october-2026.md), [Português](https://newsverum.com/pt/news/i80-gold-nevada-development-plan-update-october-2026.md)

*The source does not state the event date; the period shown is the source review period.*

i-80 Gold on October 14 updated its Nevada development plan. The company said production mining at the Archimedes underground mine remains targeted for the fourth quarter of 2026; demolition at the Lone Tree plant is complete and construction mobilization is planned for that quarter. Mineral Point open pit was prioritized as the next major development project in the revised sequence.

The company set a target of 150,000–200,000 ounces per year beginning in 2028. The schedule and production range are company targets, not realized output or a reserve statement. Construction mobilization at Lone Tree is planned and has not begun.

## Data

### i-80 Gold updates development schedule for Nevada projects

i-80 Gold updates development schedule for Nevada projects

Methodology: Figures are transcribed from the source release; company plans are not presented as results.

| date | label | description | status |
|---|---|---|---|
| 2026-10-14 | i-80 Gold updates development schedule for Nevada projects | i-80 Gold on October 14 updated its Nevada development plan. The company said production mining at the Archimedes underground mine remains targeted for the fourth quarter of 2026; demolition at the Lone Tree plant is complete and construction mobilization is planned for that quarter. Mineral Point open pit was prioritized as the next major development project in the revised sequence. | occurred |

Sources: <https://www.newswire.ca/news-releases/i-80-gold-provides-a-development-update-archimedes-underground-and-lone-tree-plant-refurbishment-remain-on-track-and-mineral-point-open-pit-prioritized-in-updated-development-plan-819201421.html> · Download data: [JSON](https://newsverum.com/api/v1/articles/i80-gold-nevada-development-plan-update-october-2026/data/company-release?lang=en&format=json) · [CSV](https://newsverum.com/api/v1/articles/i80-gold-nevada-development-plan-update-october-2026/data/company-release?lang=en&format=csv)

## Sources

- [i-80 Gold Corp. (CNW)](<https://www.newswire.ca/news-releases/i-80-gold-provides-a-development-update-archimedes-underground-and-lone-tree-plant-refurbishment-remain-on-track-and-mineral-point-open-pit-prioritized-in-updated-development-plan-819201421.html>) (Source checked: 2026-10-15; Published: 2026-10-14)

---