# CRE approves 2,500 MW of new connection capacity for Fos-Lavéra

> France’s regulator approved shared grid works intended to add 2,500 MW of connection capacity in Fos-Lavéra. With 600 MW existing, total capacity reaches 3,100 MW; gross cost is estimated at €636.4 million.

- Canonical URL: https://newsverum.com/en/news/france-cre-approves-shared-grid-connection-capacity-fos-lavera-2026
- Publisher: Newsverum
- Section: Energy
- Country: France
- Published: 2026-10-15T21:30:20+00:00
- Updated: 2026-10-15T21:30:20+00:00
- Event / data period: 2026-10-08
- Other editions: [Türkçe](https://newsverum.com/tr/news/france-cre-approves-shared-grid-connection-capacity-fos-lavera-2026.md), [العربية](https://newsverum.com/ar/news/france-cre-approves-shared-grid-connection-capacity-fos-lavera-2026.md), [Français](https://newsverum.com/fr/news/france-cre-approves-shared-grid-connection-capacity-fos-lavera-2026.md), [Español](https://newsverum.com/es/news/france-cre-approves-shared-grid-connection-capacity-fos-lavera-2026.md), [Deutsch](https://newsverum.com/de/news/france-cre-approves-shared-grid-connection-capacity-fos-lavera-2026.md), [Português](https://newsverum.com/pt/news/france-cre-approves-shared-grid-connection-capacity-fos-lavera-2026.md)

France’s energy regulator CRE approved a shared electricity connection zone in Fos-Lavéra on 8 October. The decision authorizes transmission operator RTE to anticipate and share works for new consumer and public distribution-network connections.

The plan aims to add 2,500 MW by end-2029 to 600 MW of existing residual capacity. CRE estimates gross works costs at €636.4 million in 2025 economic conditions. This is not solely the amount billed to new users: the decision sets chargeable costs and a per-MW contribution separately. The capacity does not establish that all anticipated industrial demand will materialize.

## Data

### CRE approves 2,500 MW of new connection capacity for Fos-Lavéra

CRE approves 2,500 MW of new connection capacity for Fos-Lavéra

Methodology: Figures attributed to CRE. MW denotes connection, not generation capacity; cost is estimated.

| date | label | description | status |
|---|---|---|---|
| 2026-10-08 | CRE decision | CRE authorized shared works intended to add 2,500 MW of industrial connection capacity by end-2029. With 600 MW existing, total is 3,100 MW; gross cost is estimated at €636.4 million. | occurred |

Sources: <https://www.cre.fr/fileadmin/Documents/Deliberations/2026/261008_2026-203_Zone_de_mutualisation_Fos-sur-Mer.pdf> · Download data: [JSON](https://newsverum.com/api/v1/articles/france-cre-approves-shared-grid-connection-capacity-fos-lavera-2026/data/grid-decision?lang=en&format=json) · [CSV](https://newsverum.com/api/v1/articles/france-cre-approves-shared-grid-connection-capacity-fos-lavera-2026/data/grid-decision?lang=en&format=csv)