# England reports completed cladding work on 40% of monitored buildings

> Cladding remediation was complete at 1,878 of 4,732 monitored residential buildings at least 11 metres high in England at the end of September 2026, according to a release published on 28 October.

- Canonical URL: https://newsverum.com/en/news/england-cladding-remediation-september-2026-progress
- Publisher: Newsverum
- Section: Infrastructure
- Country: United Kingdom
- Published: 2026-10-28T16:15:12+00:00
- Updated: 2026-10-28T16:15:12+00:00
- Event / data period: 2026-09
- Other editions: [Türkçe](https://newsverum.com/tr/news/england-cladding-remediation-september-2026-progress.md), [العربية](https://newsverum.com/ar/news/england-cladding-remediation-september-2026-progress.md), [Français](https://newsverum.com/fr/news/england-cladding-remediation-september-2026-progress.md), [Español](https://newsverum.com/es/news/england-cladding-remediation-september-2026-progress.md), [Deutsch](https://newsverum.com/de/news/england-cladding-remediation-september-2026-progress.md), [Português](https://newsverum.com/pt/news/england-cladding-remediation-september-2026-progress.md)

Cladding remediation was complete at 1,878 of 4,732 monitored residential buildings at least 11 metres high in England at the end of September 2026, according to a release published on 28 October. The completed share was 40%. The monitored total increased by eight buildings from August.

Work had started or finished at 2,621 buildings, representing 55% of the monitored group. The department said its programme totals cannot simply be added because some buildings appear in more than one programme. A change to social housing data collection also limits comparisons with figures before December 2025.

In the separate aluminium composite material programme, 481 of 516 high-rise residential and publicly owned buildings had completed remediation as of 1 October. Of the 516, 460 had building-control sign-off. Completion of physical works and receipt of formal sign-off are therefore different measures, and these programme counts should not be added to the overall total.

## Data

### Source publication

Publication of the official announcement on 28 October 2026.

Methodology: The date records publication of the cited official source. It does not establish completion of announced future actions.

| date | label | description | status |
|---|---|---|---|
| 2026-10-28 | England reports completed cladding work on 40% of monitored buildings | Cladding remediation was complete at 1,878 of 4,732 monitored residential buildings at least 11 metres high in England at the end of September 2026, according to a release published on 28 October. The completed share was 40%. The monitored total increased by eight buildings from August. | occurred |

Sources: <https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-september-2026/building-safety-remediation-monthly-data-release-september-2026-accessible-version> · Download data: [JSON](https://newsverum.com/api/v1/articles/england-cladding-remediation-september-2026-progress/data/source-announcement?lang=en&format=json) · [CSV](https://newsverum.com/api/v1/articles/england-cladding-remediation-september-2026-progress/data/source-announcement?lang=en&format=csv)

## Sources

- [Ministry of Housing, Communities and Local Government, UK](<https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-september-2026/building-safety-remediation-monthly-data-release-september-2026-accessible-version>) (Source checked: 2026-10-28; Published: 2026-10-28)

---